How to Write an RFQ: Format and Sections

8 min read

How to write a request for quotation suppliers can answer accurately: the standard RFQ format, what to put in each section, sample wording, and the mistakes that make quotes incomparable.

01

What a good RFQ achieves

A well-written RFQ is a request for quotation that is clear enough for every supplier to price the same requirement, in the same format, by the same deadline.

The test of an RFQ is not how professional it looks. It is whether the quotes that come back can be compared without a round of follow-up calls. When they cannot, the cause is almost always in the RFQ: an ambiguous specification, an unstated assumption about taxes or freight, or no format for the price. Each gap is filled by the supplier's own assumption, and different suppliers assume different things.

A good RFQ also saves suppliers time, which improves who responds and how seriously they respond. Suppliers decide quickly whether a request is worth their effort. A clear, complete document signals a buyer who runs a fair process. If you want the surrounding process, see the RFQ process step by step.

02

RFQ format at a glance

There is no single legal standard for an RFQ layout, but most good ones follow the same anatomy. Use the table as a skeleton and adapt the detail to your category.

Anatomy of an RFQ: what each section contains and why it matters
SectionWhat to writeWhy it matters
HeaderBuyer name, RFQ reference, title, issue date, contact for questionsLets suppliers identify and reference the request unambiguously
Instructions to suppliersHow to respond, format required, deadline, validity period, language and currencyPrevents late, incomplete or mismatched submissions
SpecificationItem description, standards, grade, tolerances, brand or equivalent policyEnsures every supplier quotes the same thing
Quantity and unitsQuantity per line, unit of measure, one-time or recurring volumeAvoids price differences caused by unit confusion
DeliveryDelivery location, required date, packaging, partial-delivery rulesMakes lead times and logistics costs comparable
Commercial termsPrice basis, taxes, freight, payment terms, warranty, validityStops hidden cost differences from distorting the comparison
Evaluation basisHow the award will be decided and any qualification criteriaLets suppliers focus on what you value
SubmissionWhere and how to submit, attachments required, deadline with time zoneGives every supplier the same route and cutoff
03

The header and instructions to suppliers

Start with the basics: your organization, a unique RFQ number, a short descriptive title, the date of issue and a named contact for questions. A reference number sounds trivial until you have five open RFQs for similar items and supplier emails refer to none of them clearly.

The instructions section tells suppliers how to respond. Cover the quotation format you expect, the language, the currency of the quote, how long the quote must remain valid, and whether partial quotes (some lines, not all) are accepted. State whether suppliers may submit alternatives and how those should be marked. Also say how and until when questions are accepted and that answers will be shared with all invited suppliers. That last line alone prevents a lot of private back-and-forth.

04

Specification and quantity: where most RFQs go wrong

The specification is the heart of the document. Describe the requirement by what it must do or meet, not just by a name. For goods, give the material, grade, size, finish, applicable standard or drawing reference, and say whether equivalents are acceptable. For services, give the scope of work, the frequency, the locations, the service levels expected and the qualifications of the people involved.

Quantity needs a unit. Ten of what? Ten pieces, ten boxes of fifty, ten kilograms? State the unit of measure on every line, and say whether the figure is a one-time order or an estimate of annual demand. If volume could change, tell suppliers, because a quote for a guaranteed volume and a quote for an uncertain one are different offers.

Where you must allow alternatives, say so, and require the supplier to declare brand, model or standard so you can check equivalence. Where you cannot, say so too. If technical documents are needed with the quote, such as datasheets, certificates or test reports, list them as required attachments.

05

Delivery, location and timeline

Delivery terms change the real price. Give the delivery address or addresses, the required date or window, any packaging or labeling requirements, and whether the goods must arrive in one lot or may arrive in stages. If delivery involves unloading, installation or commissioning, say who does what.

Be explicit about who pays for freight and transit insurance. A supplier who includes delivery in the price and one who quotes ex-works are not offering comparable numbers, and the gap can be larger than the difference you are trying to negotiate. Ask each supplier to state their delivery timeline against your required date, so a late-but-cheap quote is visible for what it is.

06

Commercial terms: price basis, taxes, payment and validity

This is the section that makes quotes comparable. Define the price basis so every supplier quotes the same way, for example unit price per line, with total, in a named currency. State whether taxes and duties should be shown separately or included. If suppliers quote in different currencies, say which currency and exchange-rate treatment you will use for comparison.

Set out your payment terms and ask suppliers to confirm them or state what they need. Ask for warranty terms and the period for which the quote stays valid. If the purchase may become a longer relationship, state the intended contract duration so suppliers can price accordingly.

Then add your terms and conditions, or attach them. If your standard terms are non-negotiable, say so up front, so a supplier does not discover them after investing time in a quote. Required supplier documents, such as registrations, certifications or references, belong here or in the instructions.

07

Evaluation criteria: tell suppliers how you will decide

Many RFQs say nothing about how the winner will be chosen, and suppliers are left to guess. State the basis plainly. If price decides among qualified suppliers, say so. If delivery time, technical suitability or payment terms carry weight, name them. You do not need to publish an internal scoring model, and for most RFQs you should not need one, but suppliers should know what the contest is about.

If some suppliers must clear a technical or compliance bar before price is considered, say that too. A two-envelope RFQ separates the technical evaluation from the commercial one, so only suppliers who qualify technically move on. Setting out qualification requirements up front, such as certifications, minimum years in business, or geographic coverage, saves everyone from quoting for work they could never win.

08

Submission method and deadline

Give one deadline, with a date, a time and a time zone. Ambiguity here breeds disputes. State whether late quotes will be rejected, and whether suppliers may update or withdraw a quote before the deadline. Explain where to send the response and what the complete response contains: the priced quotation, any technical documents, and any forms you asked for.

Email is fine for small, occasional requests. Its weakness is that sealing relies on trust and quotes arrive in whatever format the supplier prefers. A purchasing system that collects quotations through a supplier portal gives every supplier the same form and hides prices from the buyer until the deadline passes. That is where RFQ software earns its place.

09

Sample RFQ email wording

If you are sending an RFQ by email, keep the message short and attach the detail. Here is an original, neutral example you can adapt.

Subject: RFQ 2026-041, Packaging cartons, quotation required by [date and time, time zone]

Dear [Supplier name], we invite you to quote for the items listed in the attached request for quotation, reference 2026-041. Please quote per line in [currency], stating whether taxes and freight are included, your delivery timeline from order, payment terms and the validity of your quote. Please attach the specification confirmation and certificates listed in section 3. Quotations must reach us by [date, time, time zone]. Questions are welcome until [date]. Our answers will be shared with all invited suppliers. Thank you for your time.

Notice what is missing: no hints about competitors, no price expectations and no private promises. The email points to the document, and the document carries the requirement.

10

Common mistakes that make quotes incomparable

  • Describing the item by name only. Without a standard, grade or drawing, each supplier quotes their own version.
  • Leaving units unstated. Price per piece versus per pack versus per kilogram is the most common source of apparent price gaps.
  • Not defining the price basis. Taxes and freight included for some suppliers and excluded for others.
  • Hiding the evaluation basis. Suppliers cannot focus on what matters if you do not say what matters.
  • Setting an unrealistic deadline. Rushed suppliers pad prices or decline.
  • Changing the requirement mid-RFQ without telling everyone. Every change must reach every invited supplier.
  • Asking for everything. A long list of optional attachments lowers response quality; request what you will actually use.
11

A review checklist before you send

Before the RFQ goes out, read it as a supplier would. Could you price it without calling the buyer? Are units, taxes, freight, validity and deadline all stated? Is the contact named? Is the evaluation basis clear? Have you attached everything the quote depends on? The RFQ checklist turns these questions into a list you can run through each time.

Krayuv's RFQ builder walks through the same ground in order: basic information, RFQ type and deadlines, technical criteria, items, vendors and a review step. It also includes AI helpers that can draft an RFQ description and terms and run a quality check with suggestions, which are a useful second pair of eyes on the document. If you want to see it, request a demo.

Frequently asked questions

What should an RFQ include?

A header with a reference and contact, instructions to suppliers, a clear specification, quantity with units, delivery terms, commercial terms (price basis, taxes, payment, validity), the evaluation basis and the submission method with a firm deadline.

What is the standard RFQ format?

There is no single legal standard, but a typical RFQ moves from header and instructions, through specification, quantity and delivery, to commercial terms, evaluation basis and submission details. Consistency matters more than the exact layout.

How detailed should the specifications be?

Detailed enough that two suppliers would quote for exactly the same item or service. Include standards, grades, sizes or scope, and state whether equivalents are acceptable. Over-specifying brand names can reduce competition, so describe the need by function where you can.

Should the RFQ state the evaluation criteria?

Yes, at the level of what will decide the award, such as price among qualified suppliers, delivery time or technical suitability. You do not have to reveal internal working papers, but suppliers should know what the contest is about.

Can I send an RFQ by email?

Yes, and for occasional small purchases it works. The drawbacks are that quotes arrive in mixed formats, sealing depends on trust and the record sits in a mailbox. Frequent RFQs benefit from a system that collects quotations in a common format.

How do I keep quotes comparable?

Fix the specification, define units, state the currency and whether taxes and freight are included, and ask for prices per line in a set format. Share every clarification with all suppliers.

Should price validity be stated in the RFQ?

Yes. Ask suppliers to state how long their quote stays valid, and set your own minimum so you have time to evaluate and award. A quote that expires before your approvals finish is of no use.